A
Case Study in Ankara for Sustainable Office Buildings
Dr.
Ibrahim Cakmanus, Arif Kunar, Gokhan Toprak, Ayse Gulbeden
Abstract
This
paper presents a high performance, green HVAC system design optimization that
has been carried out for the new headquarters building of the ESER Contracting
and Industry Co. Inc. in Ankara. The optimum green mechanical system comprises
a multitude of renewable and sustainable mechanical components like wind
turbines, solar PV, solar collectors, ground source heat pump, energy storage
systems, and a natural gas driven trigeneration unit with absorption chiller
unit. The combined heat and power unit (CHP) follows the electric power load of
the building and also drives the ground source heat pump and the absorption
chiller. Its useful heat output is mainly utilized in comfort heating. Thermal
energy storage (TES) tanks are used, namely ice, cold, and hot water tanks.
These store energy during off-peak thermal load periods by utilizing thermal
energy from the CHP unit, absorption chiller output, its waste heat, and the
ground-source heat pump. All these systems were so sized that they operate at
almost constant peak capacity day and night such that their efficiency is
maximized and pay-back period shortened. Conventional condensing peaking and
back-up boilers and centrifugal chiller systems complement the green mechanical
system of the building. Ground-source heat pump that is driven by the CHP unit
delivers comfort heating and cooling. This building also includes rainwater harvesting
and grey water recycling systems. The
goal of this green mechanical system, which is a hybrid composition of several
systems, is to achieve minimum exergy destruction and life cycle cost goals
along with the highest efficiency. Parametric studies show that such a design
approach paves a robust roadmap towards a more environment friendly, next
generation green building concept that also translates into very low-carbon
emitting building. Another primary aim in this project is to get the first LEED
certificate in Ankara.
1. Introduction
40 years ago, the chart given in Figure 1 has been established
by Malcolm Wells, the architect, to show the sustainability in buildings. (1). While
the negative aspects in this table are generally continuing despite the current
technological developments, still new building technologies named as green,
sustainable or energy efficient buildings, are being tried to be developed. At
this connection, the buildings are classified as Gold, Platinum and Silver in
according to the LEED certification or, A, B,…..G in according to the “Energy
Performance Regulations in Buildings” in Turkey.

Figure 1. Evaluation of a typical project using Malcolm Well’s “absolutely constant incontestably architectural value scale”. The value focus was wilderness; today it might well be sustainability (1).
In LEED and BREEM classification systems, some other important aspects such as materials used, carbon footprints, land use, water use as far as the energy performance of the building, have been taken into consideration in sustainability scoring of the building. LEED rating procedures which are used in this building are summarized in table 1.



|
1. Relationships between design intent, design criteria and according to LEED
design tools/methods ratings were used for
this building. |
||||
|
Issue |
Design
intent |
Possible
design criterion |
Potential
design tools |
Potential
implementation method |
|
Sustainable sites |
Erosion and sedimentation control |
Site selection, alternative transportation, etc. |
|
|
|
Thermal comfort |
Acceptable thermal comfort |
Compliance with ASHRAE standard 55-2004 |
Standard 55 graphs/tables or comfort software |
Passive climate control and/or active climate
control |
|
Indoor air quality |
Acceptable indoor air quality |
Compliance with ASHRAE standard 62.1-2001 |
Standard 62.1 graphs/tables or comfort software |
Heat recovery, control strategies |
|
Lighting level |
Acceptable illuminianca levels |
Compliance with recommendations in the ESNA Lighting
handbook |
Hand calculations or computer simulations |
Envelope strategies and/or equipment strategies |
|
Energy efficiency |
Minimal energy efficiency |
Compliance with ASHRAE standard 90.1-2004 |
Handbooks, simulation software, manufacturer’s data,
experience |
Envelope strategies and/or equipment strategies,
heat recovery |
|
Energy efficiency |
outstanding energy
efficiency |
Exceed the minimum requirements of ASHRAE standard
90.1-2004 by 30% |
Handbooks, simulation software, manufacturer’s data,
experience |
Envelope strategies and/or equipment strategies |
|
Water efficiency |
Rain water, grey water |
|
Handbooks, software, manufacturer’s data, experience |
equipment strategies |
|
Green design |
Obtain green building certification |
Meet the requirements for LEED gold rating |
LEED materials, handbooks, experience |
Any combination of approved strategies to obtain
sufficient rating points |
2. ESER Contracting and Industry Co Inc. Headquarters Building
2.1. Architectural
Characteristics
The building is designed in according to the building
and construction codes and regulations, satisfying the utilization purposes and
needs and particularly sensitive to the energy economy and environmental and climatic
conditions. The building scheme is constituted by the spaces formed around one main
core and 2 circulations cores. The building briefly includes;
-
2nd basement in which a car-park for 51
cars take place.
-
General services and annexes spaces, conference salon,
cafeteria, and 1st basement which includes various offices and
storage spaces,
-
Ground floor which include the entrance, main hall
with gallery, protocol entrance, cafe/waiting salon and the offices,
-
1st floor which include gallery space,
small meeting rooms, and offices,
-
2nd and 3rd floors which include
floor-hole, small meeting rooms, open and private offices,
The roof space includes floor hall, guest rooms,
meeting saloons and private office rooms. The building has totally 7 storeys. Total
construction area of the building is
In the outer cover of the building, natural heat and sun control have been provided by using different materials and construction details in east, west, south and north façades. Particularly in the insulation details, in addition to the national codes, the materials and methods in according to the international standards have been used. In the selection of the building materials, the criteria such as environment, sanitation, hygiene, availability in nearest region, local product utilization and recycling have been taken into account. Various views from the building, putted in service in 2010, are given in Figure 2.



Figure 2a. Various views of Eser Headquarter Building.
3. Climatic Conditions
For
Ankara;
Dry bulb temperature for winter: -12 ºC
Dry-bulb temperature for summer: 33ºC
The building is in service between the hours 8.30/18.30.
Internal comfort temperatures: 22ºC (winter) and 24ºC (summer)
4. Energy
Performance of the Building
To increase the energy performance of the building the
precautions mentioned below are necessary;
a) suitability
of the projects to the codes and standards,
b) selecting
of high energy performance devices in the building,
c) following
the projects strictly,
d) establishing
automation scenarios and providing the system operations in according to the
projects and scenarios.
In addition to
the energy efficiency in building performance, the effects of internal air
quality, day lighting, and noise are also important issues. For the purposes of
increasing energy performance of the building the insulation thicknesses of
In addition, renewable energy resources and
trigeneration system also have been used for the purpose of increasing the
energy performance of the building. The typical daily heat loads of the
building for winter and summer months have been shown in Figure 3a and 3b. These
variable loads are satisfied by a base-load CHP and GSHP system, three natural
gas (NG) condensing boilers, and TES systems year-round. 100 kW GSHP+CHP
combination operates above 7500 hours in a year on a base load both in heating
and cooling mode. Boilers are operated in tandem thus permitting to maintain
their maximum thermal efficiencies. The same is also true for GSHP+CHP
combination.
4.1.
Hybrid
Tri-Generation System
The most important parameter in reducing carbon emissions effectively in high-performance buildings is to match the source exergy with the demand exergy of the building. In this respect, the first fold in this quest is to reduce the exergy demand of a building. If this can be achieved, the building becomes a low-exergy building. While the building approaches a low-exergy condition, solar, wind, waste heat and similar sustainable energy resources, which are also low-exergy type, become feasible to match with the building demand. In this case the so-called Rational Exergy Management Model Efficiency increases and consequently the direct and avoidable carbon emissions reduce substantially [2]. In a typical office building heated by a natural-gas boiler system and air-conditioned with a conventional chiller system, this efficiency is not greater than 6% (3). This is due to the fact that the high exergy natural gas and high exergy electric power is used to satisfy low-exergy demanding comfort cooling and cooling functions. A low-exergy building may reduce power and fossil fuel use simply by enabling the alternative energy resources temperature compatible with the building demands. In ESER building, a novel balancing philosophy was employed (2). This balancing act, which relies on temperature cascading of supply and demand is shown in Figure 4. The implementation of this balancing act increased the rational exergy management efficiency from 6% to 55% minimum. This means that the carbon emission reduction potential compared to a conventional system using natural gas both at the boiler (on-site) and at the power plant (off-side) is reduced by a factor of 2.1, that is shown in equation 1 (3). This factor does not include the contribution of ground heat through the heat pump, solar energy and the wind power. Together with heat recovery and all these, the total carbon emissions reduction factor is estimated to be more than 4.

Figure 3a. Load profile of the building-winter.
Figure
3b. Load profile of the building-summer.


Figure 4. Exergy balancing act in ESER Building in terms of temperature cascaded applications.
According to Figure 4, the core of the supply system
is a natural-gas CHP unit with a natural gas motor which follows heating demand
(4). Electric power produced is complemented by solar and wind energies. Power
is mainly used to drive the ground-source heat pump (GSHP). GSHP adds additional
heat produced by the CHP unit. In summer GSHP produces cold energy and stores
thermal energy obtained while cooling the building in the ground for the next
heating season (Seasonal TES). Daily and hourly TES systems help to shave-off
the thermal loads of the building. Heat and cold first go the respective TES
tanks in the mechanical room. In order to increase the COP of the GSHP, it is
operated at moderate temperatures (low-exergy supply mode). CHP unit however
provides hot water at higher temperatures (high-exergy). Therefore in the
heating mode two different TES tanks are used. One is low-exergy; the other is
high-exergy. The similar approach is employed in cooling; while GSHP provides
moderate cold (to cold storage); undersized conventional chillers are used on
demand to maintain the ice storage tank. In summer the excess heat from the CHP
unit is utilized in an absorption chiller. Solar collectors are primarily used
to satisfy DHW loads.
4.1.
Annual
Energy Consumption
Winter
Operation: The average hourly heating energy needed is
approximately 200 kWh which can be seen in Figure 3a (3). This valued includes
the heating energy of fresh outside air too.
The winter operating hours of an office building in Ankara can be taken
as 1200 hours. Therefore the annual total heating energy demand can be
calculated as 240.000 kWh. In this connection the energy demand for just
heating has been calculated as 165.000 kWh. This value is 50% less than
threshold value for Ankara given in national standard TS 825 (3rd region
of Turkey).
Summer
Operation: Hourly cooling energy has been accounted as 200 kW
from Figure 3b, with a safety factor. This figure includes the cooling energy
for cooling the fresh outside air too. The average operation period in summer
for an office building in Ankara can be taken as 800 hours. Then, the total
annual cooling energy is 160.000 kWh which is included ventilation consumption.
Study
of total energy consumption: The annually total energy
consumption of the building, ventilating included, is approximately (240.000+160.000=)
400.000 kWh/year, and the energy demand per square meter (m2) is
calculated as (400.000/5000 m2=) 80 kWh/m2year. This
figure is 50% less than the similar buildings in Ankara (5). This calculation
did not include the reduction by the heat recovery device in the ventilating
system. To meet the heating and cooling
loads of the building a high efficiency flow chart has been used (Figure 4). As
can be seen from Figure 3a and 3b, the 50 kW portion of base load will be met
by heat-pump and for another 50 kW portion, the waste heat from cogeneration
unit will be used. The coefficient of performance (COP) of the heat pump is 2,5
and the COP value with pumps and thermal storage included, has been assumed as
1,5. The 20 kW portion of the electrical
energy from cogeneration unit, feeds the compressor of the heat pump (summer
and winter). The waste heat of the cogeneration unit is used in absorption
chillers in summer, it is used for air-handling units and VRV (Variable
Refrigeration Flow) system via thermal storage system.
At the times in which the electricity demand exist but
heating demand inexist, the heat from ground source heat pump and cogeneration
unit have been stored and used in case of heat demand. When there is no cooling
demand, i.e. at night times, cooling energy is stored. In case of excess
thermal energy needs in winter the condensation boilers and in case of excess
cooling energy demand in summer the air-cooled condensation units and ice-storage
system are being put into operation. The chilled and hot water generated by
these systems are transferred to the outside units of VRV system by plate heat exchangers to meet
the heating and cooling loads. While the COP of the VRV system has been assumed
as 4,5 and COP of the whole VRV system (pumps included) has been taken 3,5. The
heating demand of air-handling-units in winter has been met by the waste heat
of the cogeneration device and the boilers. The cooling need in summer has been
satisfied by the absorption chiller and air cooled chiller.
5. Operating
Performance
5.1. Control
of Air Quality
Until the contamination in the
space is lowered to an acceptable level, air-handling units are operated in
100% rpm. Then, when the VAV dampers are moved to close position depending on
the signals from CO2 sensors, the rpm’s of the fans are reduced by
frequency converters and maximum energy savings are obtained partly closing the
2-way valve of heating and cooling coils. Here, 2-way valves of the air
handling units (AHU’s) are positioned in according to the temperature of supply
air.
5.2.
Energy Monitoring, Measuring And Modeling
These instruments have been used for the purpose
defining the progressing of energy savings, understanding the building base
load, reducing the operating expenses and cheking the load profile. For this
purpose, various points of the installations energy analyzers, temperature and
pressure sensors gas and water flowmeters, air quality sensing elements have
been placed and linked to the Building Automation
System (BAS). the data obtained from these instruments, the efficiency of the
devices and systems; energy consumption per m2 and water consumption
per capital can be calculated and monitored. In the plant, the saving
potentials of these areas can be investigated and if there is, the necessary
precautions will be taken.
5.3. Heating and Cooling Systems in Building
As noted above, the in-building installations
that the heating and cooling systems served are; a) VRV system), b) heating coils
of AHU’s, c) Floor heating circuit, d) domestic hot water system (DHW).
VRV system: This system is operated by its control system. Here,
the outside unit has been adjusted between 25-30ºC in winter and 15-20ºC in
summer, in the directive of manufacturer. In winter, when the water temperature
goes below 25ºC the different stages of heating system (thermal storage,
heat-pump, cogeneration unit, and the boilers respectively) are being put into
operation.
Air Handling Units (AHU’s): The coils of the air handling
units need higher temperatures than that of VRV system needs, depending on the
outside temperature. While, in heating the water temperature regime of this system
is 80/60ºC, this figure will reduce when the outside temperature rises. The
operation regime of these circuits in cooling has been taken as 8/13ºC.
Floor Heating Loop: Hot water regime in the loop is approximately 55/45ºC
and it can be fed from the heat pump. Here energy savings will be provided by
placing 2-way valves in either floor.
Domestic Hot Water Heating Loop: In summer,
there will approximately be 45ºC water in the storage. In addition, for the
sake of Legionella occasionally heating will be made up to 70ºC. The system will be mainly fed from solar
collectors and supported by boilers in winter and by the waste heat of
absorption chillers or boiler in summer.
5.4. Boiler Plant and Central Cooling Systems
Heating systems: a) Heat pump, b) cogeneration unit, c) boilers, d) thermal
storage, e) solar collectors.
Heat pump: It
will operate to meet the hating base load in all heating period. When there is
no heat extraction from VRV and when the thermal storage temperature is higher
than 45ºC, the circulation pumps of the heat pump will stop and there will be
no generation. At this period, when the return water temperature is higher than
45ºC the heat extraction from storage tank will commence.
Cogeneration: The waste heat of this device will be used supporting
the heating needs of VRV outside units and air-handling units.
Boilers: This system will operate to support the heating
system (VRV, floor heating, air handling units, DHW) when the heat pump and
cogeneration unit is not sufficient to meet the heating demand of the building.
In this connection, when the cogeneration unit is not sufficient, the coils of
air handling units will be fed by the boilers. Cascade boilers will be put into
operation sequentially.
Thermal Storage: When there is no heating demand, the ground source
heat pump will storage heat in the low temperature water tank in heating
period. Because of the temperature regime,
this system will provide hot water to the outside units of VRV. When the
temperature of the storage tank reached to 55ºC, the heat pump will stop. In
the periods that there is no heating demand in the building, thermal storage
will be implemented from cogeneration device to the tank. This system will feed
the heating coils of air handling units.
Operating Principles of Heating System:
VRV and floor heating system will be fed by ground
source heat pump basically. When the heat pump are operating in full capacity,
if the return water temperature drops below 43ºC for a definite time duration
the cogeneration unit will start operating.
During night times, the heat pump will feed the storage tanks. At the
moment at which the temperature exceeds 55ºC, this feeding process will
terminate. In addition when the return temperature of the system drop below
50ºC for definite time duration the capacity of the heat pump system will be
reduced or it will be stopped. When the 2-way valves of air handling units is
fully-closed in an adjusted duration, the waste heat will be used in thermal
storage. When the 2-way valves of AHU’s are fully open, the return water
temperature is remained below 55ºC for an adjusted time duration and the
blowing air temperature to the spaces cannot reach the set value, the boilers
will be put into the operation sequentially.
Cooling Systems: a) Heat pump, b) cogeneration unit, c) absorption chiller,
d) air-cooled chiller, e) thermal storage (ice and chilled water).
Heat Pump: It will meet the basic cooling load in cooling season.
During the night times, when there is no cooling demand it will operate for
thermal storage. When the temperature of the water in the tank rises to 9ºC,
water will directly be sent to the system.
Cogeneration unit: The waste heat of this device will be used to support
the heat demand needs by absorption chiller. In night times, when there is no
cooling demand it will operate to store cooling energy via absorption chiller.
Absorption Chiller: This unit chiller will be used for the utilization of
the waste heat of cogeneration device (for VRV and AHU’s). When there is no
sufficient solar energy domestic hot water system will be fed. In case of
insufficient waste heat of cogeneration, the boiler support will be provided.
The operating regime of the chiller circuit of cooling machine is 8/13ºC.
Air-cooled chiller: This unit will operate to support the load (VRV and
AHU’s), when the cogeneration unit and heat pump is not sufficient to meet the
load. The operating regime of the chiller is 8/13ºC. This unit will also be
used to store ice in hot summer days.
Thermal Storage:
Cooled
water storage: During the night times, when there is no cooling
demand, cogeneration device and the ground source heat pump will store cooling
energy (together with absorption chiller). During the daytimes primarily these
storage will be used. When the temperature in the storage tank rises higher
than 10ºC (setting is available for the value), cooling energy will be extract
from ice-storage tank (if any) and/or the heat pump will be put into
operation.
Ice storage: During the daytimes, when the temperature is high, the
system will operate from ice storage system. And during the night times, taking
the advantage of lower electricity price the system will operate to store ice
(cooling energy).
6. Plumbing Systems
The
solar collectors have been used to generate domestic hot water and the boilers
have been designed to support the system. Rain water has been collected and
used in gardening activities. In
addition, the grey waters from the lavatories have been purified and used in
the reservoirs.
7. Lightening and Electricity
High efficiency bulbs and apparatus have been used in artificial lightening.
The type of the electric motors are high efficient type (EFF1). The BAS and the electrical installation have
been designed so that the air conditioning system can be operated efficiently.
8. Renewable Energy
For the purposes of taking advantage of the natural lightening,
day-lighting shafts have been constructed in the building. PV units and wind
turbine are installed to meet electrical needs of the building partly. All
these systems are shown in Figure 2.
9. Conclusion
The systems
described above have increased the initial investment cost by 15%. On the other
hands, improvements in the façades of the building, heat recovery systems,
renewable energy technologies, combined heat and power (CHP) systems and
efficient HVAC utilizations and efficient operation of these systems has
reduced the fossil fuel consumption, CO2 emissions and life cycle
cost of the systems.
Acknowledgement
We would like to mention our special thanks to the personnel of OSTIM
Investing Corp. who shared their experiences with us and Mr. Prof. Dr. Birol
Kilkis, who is a member of High Performance Metrics of ASHRAE and the academic
member of Başkent University.
References
[1] Stein
B., Reynolds, J. S.. Grondzik, T. W., Kwok, G. A., 2006, Mechanical and
Electrical Equipment for
Buildings, John Wiley and Sons Inc., Canada.
[2] Kılkış, Ş. 2009. Kılkış Ş. “A Rational Exergy Management Model for Sustainable Buildings to Reduce Compound CO2 Emissions”
Proc/e 40th Congress on HVAC&R – KGH, pp. 391-412.
[3] Kılkış, B., 2009, “What is a High Performance Building and What
is not? Description, Definitions and
Basic Functions”, TTMD
Journal, March-April 2009.
[4] Jalalzadeh, A., 2007, “A Comparison of Electrical and Thermal Load
Following CHP System”, TTMD Journal, March-April 2007.
[5]
Çakmnaus, I., 2007, “Natural ventilation of existing buildings
regarding to energy efficiency: An example in Ankara- Turkey”, REHVA World
Climate Congress, Helsinki.
